QA Programs, Responsibilities and Records

Construction Quality Assurance Expert

A construction quality assurance expert evaluates the oversight that others provide to confirm that a contractor's quality control is working: owner representatives, construction managers, design professionals and third-party inspectors. Paul Gaston identifies what each party's quality assurance role actually was under its contract, what it did, and how that oversight relates to the contractor's own responsibility.

A small crew in hard hats standing inside a large steel frame building beside a mobile crane

Who Provides Quality Assurance

PartyTypical quality assurance roleUsual limits
Owner or owner's representativeObserves progress and quality on the owner's behalfDefined by the owner's own procedures and contracts
Construction managerMonitors contractors' work and quality programsDefined by the construction management agreement
Architect or engineerSite observations to determine general conformance with design intentUsually not continuous or exhaustive inspection
Building officialInspects specific code items at required stagesCode compliance only, at defined points
Third-party inspectorInspects specified items under its scopeLimited to its contracted scope

The actual roles depend on the contracts, which Paul reads before evaluating any party's conduct.

Quality Assurance Does Not Replace Quality Control

A common argument in quality disputes is that the owner, architect or inspector should have caught a problem. Sometimes their role did include that check. Often it did not, because their contracts limit them to periodic observation or to specific items. Under most construction contracts, the contractor remains responsible for the conformance of its work whether or not anyone else noticed a problem. Paul explains what each party was responsible for, so that arguments about who should have caught a deficiency rest on the documents rather than assumptions.

Quality Assurance Programs

Larger owners, public agencies and institutions often run formal quality assurance programs, with inspection schedules, reporting forms, audits of contractor quality control and acceptance procedures. Paul's experience with City of Chicago facilities and the Department of Aviation gives him practical familiarity with how such programs work. He reviews the program documents and records to determine what the program required and whether it was carried out.

A drone flying over a concrete building under construction while a worker in an orange jacket watches
A construction worker in a white hard hat and vest holding plans inside a concrete structure under construction

Quality Assurance Records

Quality assurance generates its own records: observation reports, field reports from design professionals, inspection reports, audit findings, nonconformance notices and acceptance documents. These records show what the overseeing party saw and when. They can corroborate or contradict the contractor's quality control records, and they can show whether known issues were communicated to the contractor and followed up.

Allocation Questions

Where several parties had some quality role, the question of who bears responsibility for a missed deficiency is ultimately for counsel and the court. Paul's contribution is a clear description of each party's documented role, what it did, and what it knew. See construction quality control and construction inspection failures.

Questions

Common Questions

Is the architect responsible for catching construction defects?

Usually only to the extent the architect's contract provides, which is often periodic observation for general conformance, not exhaustive inspection. Paul reviews the contract to determine the actual role.

Does owner oversight reduce the contractor's responsibility?

Under most contracts the contractor remains responsible for conforming work regardless of owner oversight, but the contracts control.

What records does quality assurance produce?

Observation and field reports, inspection reports, audit findings, nonconformance notices and acceptance documents.

Does Paul decide who is liable for a missed defect?

No. He describes each party's documented quality role, what it did and what it knew. Allocation is for counsel and the court.

Does the dispute turn on what was inspected and recorded?

Send the party names for a conflict check. Paul will review the quality records and the work and explain what they show.